Location | BER Airport, Schönefeld |
Client | Flughafen Berlin Brandenburg GmbH |
Planung | GMP Architekten |
Execution time | 2013 – 2021 |
Service | object supervision and site management, LP 8 |
Project leader | Marko Mühmel, Christian Werner und Mario Iliades |
Projektbeschreibung | Mehr Infos |
Project description
A small city with independent energy supply and its own technical infrastructure, which is largely completed. This means that all four media to be provided by the energy central (CHP electricity, emergency power, heat and cold) can be called up. The data center can be used since the beginning of November and was therefore available on time for trial operation. In March, the topping-out ceremony for the new security building was celebrated.
Airport security, federal police and customs will share the building with commissioning, which will allow for optimal cooperation. The security building was completed on October 30, 2011. In total, there are 10 buildings of various sizes.