Charité – Virchow Clinic
Location | Campus Virchow Klinikum, Berlin |
Client | Charité – Universitätsmedizin Berlin |
Design | Heinle, Wischer und Partner |
Execution time | 2016 - 2017 |
Construction costs | 19,8 Mio. EUR |
Service | Project management |
Project leader | Christian Werner |
Projektbeschreibung | Mehr Infos |
Project description
Project management for the rehabilitation of the electrical engineering infrastructure at the Campus Virchow-Klinikum (CVK).
The project comprises the subsectors – Stabilization of the Northern Barrage, Central Technical Supply, Stabilization of Central Areas and Stabilization of the Cardiological Clinic and the Biobank.
Implementation will take place in several construction phases, renewal of the transformer stations, refurbishment of the cable trays, integration of the combined heat and power plant, creation of a new medium-voltage ring, integration of the transformer stations.
The challenge of the measures is the implementation on the fly.