Pressing plant Mercedes-Benz

Location Sulzbacherstraße, Bremen
Client Daimler AG
Design kohlbecker architekten
Execution time 2011 – 2013
Size NFA 16.000 m²
Construction costs 16 Mio. EUR
Service object supervision, LP 8
Project leader Andreas Cimander / Daniel Petry
Projektbeschreibung Mehr Infos arrow_drop_down

Project description

Daimler AG is expanding its existing press shop, Building 5, to build a 40m axle to create a new press. West of the building 5 is still a 1-storey logistics hall arise. The 2-storey building is divided into the following functional areas:

– Ground floor: material supply, scrap disposal
– First floor: production
– Technical floor: roof central
– Basement: channels for scrap disposal, escape tunnel